Title: Designing high-speed train railway embankments using finite element analysis
Authors: Egeli, İsfendiyar
Usun, Handan
Keywords: Embankment design
Fill settlements
High-speed trains railways
Publisher: Springer Verlag
Source: Egeli, İ., and Usun, H. (2012). Designing high-speed train railway embankments using finite element analysis. Arabian Journal for Science and Engineering, 37(8), 2127-2136. doi:10.1007/s13369-012-0302-6
Abstract: Design and construction of high-speed train railway (HSTR) infrastructure is different from that for normal trains, since high geometric standards and material properties are involved. For example, HSTR embankments are designed to limit total-differential settlements to minute amounts. In this study, a typical 'slab-track' type HSTR embankment was used to investigate the replaceability of one fill strata known as 'uncemented-prepared-subgrade layer' (U-PSL), constructed by using a locally obtained medium sand, as opposed to various 'cemented-prepared-subgrade layers' (C-PSL), whose mixes were prepared at two water-to-cement (w/c) ratios and three cement contents (c). Three size cylindrical samples were cast, 7-28 days water cured and were tested to obtain the unconfined compressive stresses, strains, elasticity moduli and Poisson's ratios at failure. Test results were then fed into the Plaxis-FEM program to find the maximum total settlements of individual layers and compared with the requirements. Only three C-PSL mixes having cement contents (c) of 20, 25, 30 % and water-to-cement (w/c) ratios of 0. 4 and 0. 5 met the strict settlement criteria. The study showed that the original (h = 2 m) thick U-PSL can be replaced with 0. 3h-m thick C-PSL at w/c = 0. 5 (i. e. h = 0. 6 m). Likewise, the original (h = 2 m) thick U-PSL can be replaced with 0. 2h-m thick C-PSL at w/c = 0. 4 (i. e. h = 0. 4 m). Also, the extra effort of doing in situ soil compaction and testing in layers is reduced or eliminated. This would give not only alternative ways to HSTR embankment designers/constructors, but also substantial savings in construction time and costs.
URI: http://doi.org/10.1007/s13369-012-0302-6
http://hdl.handle.net/11147/5612
ISSN: 1319-8025
Appears in Collections:Civil Engineering / İnşaat Mühendisliği
Scopus İndeksli Yayınlar Koleksiyonu / Scopus Indexed Publications Collection
WoS İndeksli Yayınlar Koleksiyonu / WoS Indexed Publications Collection

Files in This Item:
File Description SizeFormat 
5612.pdfMakale1.18 MBAdobe PDFThumbnail
View/Open
Show full item record



CORE Recommender

SCOPUSTM   
Citations

3
checked on Mar 22, 2024

WEB OF SCIENCETM
Citations

4
checked on Mar 23, 2024

Page view(s)

122
checked on Mar 25, 2024

Download(s)

282
checked on Mar 25, 2024

Google ScholarTM

Check




Altmetric


Items in GCRIS Repository are protected by copyright, with all rights reserved, unless otherwise indicated.